- All the electrical is in
- Waste plumbing was completed
- Vent plumbing was completed
- Insulation and vapour barrier for the Main floor was completed
- Half of the ceiling in the Main floor has insulation and vapour barrier
- Half of the insulation in the basement is installed
By the time I return to posting... Oct 20th the following needs to be completed:
- All the insulation and vapour barrier everywhere...
- Water supply lines to the bathrooms and the kitchen