Lot's have been accomplished up at the Cottage this past week, including:
  • All the electrical is in
  • Waste plumbing was completed
  • Vent plumbing was completed
  • Insulation and vapour barrier for the Main floor was completed
  • Half of the ceiling in the Main floor has insulation and vapour barrier
  • Half of the insulation in the basement is installed
But alas you will have to wait until next week to get the details, as I am traveling to Halifax this week and don't have access to my computer.

By the time I return to posting... Oct 20th the following needs to be completed:
  • All the insulation and vapour barrier everywhere...
  • Water supply lines to the bathrooms and the kitchen